Notice to Resume Work or of Measures Satisfied – Trans Mountain Pipeline ULC – Order RRW-001-2024

Notice to Resume Work or of Measures Satisfied – Trans Mountain Pipeline ULC – Order RRW-001-2024 [PDF 69 KB]

NOTICE TO RESUME WORK OR OF MEASURES SATISFIED,
IN THE MATTER OF THE CANADIAN ENERGY REGULATOR ACT,
FOLLOWING AN ORDER UNDER SECTION 109(1)

The undersigned Canada Energy Regulator Inspection Officer hereby notifies:

Trans Mountain Pipeline ULC that the hazardous or detrimental situation described in Order No. RRW-001-2024 has been remedied to the satisfaction of the Inspection Officer.

Therefore,

  •     suspended work may resume, and/or
  •  X  the measures specified in the Order have been satisfied.
Inspection Officer

Inspection Officer

20 March 2025

Date


-

Information not available

IO Designation Number

210-517 10 Ave SW, Calgary AB  T2R 0A8

CVA number: CV2425-351

Date modified: