Notice to Resume Work or of Measures Satisfied – Westcoast LP – Order DRP-002-2025

Notice to Resume Work or of Measures Satisfied – Westcoast LP – Order DRP-002-2025 [PDF 320 KB]

NOTICE TO RESUME WORK OR OF MEASURES SATISFIED,
IN THE MATTER OF THE CANADIAN ENERGY REGULATOR ACT,
FOLLOWING AN ORDER UNDER SECTION 109(1)

The undersigned Canada Energy Regulator Inspection Officer hereby notifies:

Westcoast LPFootnote i that the hazardous or detrimental situation described in Order No. DRP-002-2025 has been remedied to the satisfaction of the Inspection Officer.

Therefore,

  •     suspended work may resume, and/or
  •  X Specified measures 1 and 2 of the Order have been satisfied. Specified measure 3 of Order DRP-002-2025 remains in place until the corrective and preventive actions identified in measure 2 have been fully implemented, unless otherwise directed by the undersigned Inspection Officer.
Inspection Officer

Inspection Officer

12 December 2025

Date

 
REDACTED
 
 
REDACTED
 

IO Designation Number

Signature

210-517 10 Ave SW, Calgary AB  T2R 0A8

CVA or incident #: DTP2025-258 and CV2526-323

Date modified: